Something's Gotta GiveIf you rigidly define the project's schedule, budget and the scope to be delivered, you've left no room for your team to maneuver, and are headed for failure.Scott Ambler
It's your first day on a new project; you've just left the kick-off meeting and the energy is palpable: A senior vice president explained the project's importance, management promised complete support, and key stakeholders pledged their loyalty to your team, which is staffed with experts. Why, in the face of all this bonhomie, do you have that sinking feeling? Because you know that the project will fail-and there's nothing you can do about it.
Software Development Its your first day on a new project; youve just left the kick-off meeting and the energy is palpable: A senior vice president explained the projects importance, management promised complete support, and key stakeholders pledged their loyalty to your team, which is staffed with experts. Why, in the face of all this bonhomie, do you have that sinking feeling? Because you know that the project will failand theres nothing you can do about it.
The Iron Triangle
How Long Will It Take? Agile project teams organize their schedules into short iterations, typically between one and four weeks, during which they implement a subset of the requirements. The primary product is working software that fulfills the most important requirements to date. With this approach, you can set the schedule, but leave some leeway in terms of the product delivered at deadlineor you can set the scope, but allow some flexibility in the time frame. By stretching one corner of the triangle, you dramatically increase your chance of delivering a working system, at the negligible cost of additional management uncertainty.
What Will It Cost? Are you ready for a shock? I believe that annual budgets are the bane of effective management. First, they encourage people to focus on financial issues only at budgeting time. Second, they promote a bucket mentality: This year, we have $50,000 to spend on training, $10,000 for books and $20,000 for tools instead of We have $80,000 to spend wisely. Third, they create a stack of money mentality. Although thinking that you have $80,000 to spend wisely is a step in the right direction, better yet is the attitude that you should invest whatever you need to get the job done. No, you cant expect an unlimited budget, but you will spend what you have wisely and adjust your strategy as required. How can you manage project resources in an agile manner? Think of money as flowing from a tap instead of from a collection of prefilled buckets. The traditional approach is to define a project as a six-month, half-million-dollar effort. This is a fundamental mistake. Instead, give the team $100,000 for the first month. At the end of that time, evaluate their progress and base next months resources on their track record. If they did a good job, let them have $125,000; if they did a poor job, cut their budget to $75,000 and put them on notice of cancellation. Scrum is one proven method (www.controlchaos.com) that espouses this philosophy. The advantage? By directing your resources to the teams that are cost-effective, you get the most value for your investment. The disadvantage? You dont know what youre going to spendbut thats the reality of all budgets. The Canadian government recently discovered that its national gun registry project went 500 times over budget: Originally estimated at $2 million, the agency spent $1 billion before it got caught. The fundamental trade-off? To ensure that your money is spent wisely, you dont exactly know what youll get or exactly when youll get it.
What Will I Get? Agile developers invest some timeperhaps a few hours or daysinvestigating the systems initial, high-level requirements. This gives them a handle on the scope and enables them to start assigning functionality to iterations based on priority. Agile developers implement the highest-priority requirements in each iteration, ensuring that they deliver the greatest value to their stakeholders at all times. They also deliver working software in each iteration, thereby providing tangible results from the projects inception. New requirements are prioritized and put onto the stack for future iterations, enabling a simple yet effective change-management process. The primary problem? Its difficult to define exactly what youll have after six months of effortbut you do know that youll have the most important functionality built with the resources available to you at the time.
Will It Be Good Enough? Reviews, which enable other sets of qualified eyes to examine artifacts for defects, are the traditional way to guarantee quality. But is this the best approach? No. Instead of looking for defects after the fact, wouldnt it be better to create an error-free product to begin with? From the agile viewpoint, the desire to hold an inspection is an indication that youve failed to be effective elsewhere. For example, if people are qualified to validate that the system meets the corporate architecture standards, why didnt they work on the architecture at the outset? On agile projects, quality comes through collaboration. Coding standards and modeling guidelines help, as does test-first development and active stakeholder participation. Extreme Programmings practice of collective ownership is one way to promote high quality; when many eyes are on the watch, mistakes are more likely to be found and fixed. Furthermore, the use of generalizing specialists (see "Isnt That Special?", Jan. 2003) ensures that developers have a sufficiently wide range of skills to understand every aspect of the software theyre building. By promoting effective collaboration, you ensure that the qualified eyes are present from the start to ensure a high-quality product.
Its a Matter of Trade-Offs Scott Ambler is a senior consultant with Ronin International Inc. His latest book is The Elements of UML Style (Cambridge University Press, 2002).
|
|
|||||||||||||||||||||||||||||
|
|
![]() |
||||
![]() |
|
|||
![]() |
||||
![]() |
||||
![]() |
|
|||
![]() |
|
|||